HPSEBL Projection of Power Purcahse Fixed & Variable Cost per unit rate at HP periphery for January, 2022

(As on 10.01.2022)

Sr.No. Power Station Name Owner Total Installed Capacity (MW) Capacity Allocated (MW) Fixed Cost (Rs./kWh) Variable Cost (Rs./kWh) Total Cost (Rs./kWh)
1 Anta (Gas) Central ISGS 419.33 15.01 0.74 2.09 2.83
2 Anta (Liquid) 0.74 18.14 18.88
3 Anta (LNG) 0.74 10.60 11.34
4 Auraiya (Gas) 663.36 22.02 0.66 2.17 2.83
5 Auraiya (Liquid) 0.66 14.52 15.18
6 Dadri (Gas) 829.78 24.98 0.60 2.13 2.73
7 Dadri (Liquid) 0.60 20.51 21.11
8 Dadri (LNG) 0.60 9.91 10.51
9 Dadri II (Thermal) 980.00 1.76 1.49 3.47 4.96
10 Kahalgaon -II STPS 1,500.00 22.95 1.13 2.69 3.82
11 Rihand-I STPS 1,000.00 36.70 0.88 1.57 1.51
12 Rihand-II STPS 1,000.00 34.80 0.73 1.56 1.51
13 Rihand-III STPS 1,000.00 35.71 1.50 1.54 1.49
14 Singrauli STPS 2,000.00 3.40 0.68 1.58 2.26
15 Tanakpur HEP 94.20 3.08 1.71 1.71 3.42
16 Unchahar-I TPS 420.00 1.73 1.12 3.31 4.43
17 Unchahar-II TPS 420.00 12.85 1.05 3.34 4.39
18 Unchahar-III TPS 210.00 8.40 1.40 3.31 4.71
19 Unchahar-IV TPS 500.00 1.00 1.62 3.12 4.74
20 Tanda-II 1,320.00 1.85 1.58 3.09 4.67