Home  »  Reports   »   Daily Reports   »   Planned Shut Down Report

Planned Shut Down Report

Outage Showing for:-

Sr.No. Outage ID Outage type Element Name Element Type Outage Mode Reason Request Details Status
From Date From Time To Date TO Time
1 207 PLANNED Dehar 220 KV(HPPTCL)-Kangoo 220(HPPTCL) 1 LINE DAILY REPLACEMENT OF RED HOT JUMPER & TWIN CLAMP OF 220KV BUS AND OTHER MAINTENANCE WORK. 14-06-2023 10:00:28 14-06-2023 17:00:28 NOT REQUIRED
2 228 PLANNED Dehar 220 KV(HPPTCL)-Kangoo 220(HPPTCL) 1 LINE DAILY For replacement of red hot jumper & twin clamp of 220kV Bus and other maintenance work 19-07-2023 10:00:32 19-07-2023 17:00:32 PENDING
3 251 PLANNED BUS-1(GUMMA GISABS400001):400/220 kV Gumma (GIS)(HPPTCL) BUS DAILY Auto-recloser testing 01-08-2023 10:00:24 01-08-2023 16:00:24 PENDING
4 252 PLANNED Gumma(400)(HPPTCL)-Panchkula(400)(HPPTCL) 1 LINE DAILY Auto-recloser testing 01-08-2023 10:00:10 01-08-2023 16:00:10 PENDING
5 253 PLANNED Gumma(400)(HPPTCL)-Jhakri(400)(HPPTCL) 1 LINE DAILY Auto-recloser testing 01-08-2023 11:19:15 01-08-2023 11:19:15 PENDING
6 254 PLANNED Bay-408( 4876) BAY DAILY Auto-recloser testing 01-08-2023 10:00:10 01-08-2023 16:00:10 PENDING
7 255 PLANNED Bay-406( 4874) BAY DAILY Auto-recloser testing 01-08-2023 11:31:17 01-08-2023 11:31:17 PENDING
8 256 PLANNED 400/220 KV 315 MVA ICT 1(5735):400/220/66 kV GIS Gumma(HPPTCL) ICT DAILY Auto-recloser testing 01-08-2023 10:00:10 01-08-2023 16:00:10 PENDING
9 257 PLANNED 400 Kv Bus- 2 (Gumma)(1400001):400/220 kV Gumma (GIS)(HPPTCL) BUS DAILY Auto-recloser testing 01-08-2023 10:00:03 01-08-2023 16:00:03 PENDING
10 258 PLANNED Gumma(400)(HPPTCL)-Panchkula(400)(HPPTCL) 2 LINE DAILY Auto-recloser testing 02-08-2023 10:00:03 02-08-2023 16:00:03 PENDING
11 259 PLANNED Bay-405( 4873) BAY DAILY Auto-recloser testing 02-08-2023 10:00:03 02-08-2023 16:00:03 PENDING
12 260 PLANNED Gumma(400)(HPPTCL)-Jhakri(400)(HPPTCL) 2 LINE DAILY Auto-recloser testing 02-08-2023 10:00:03 02-08-2023 16:00:03 PENDING
13 261 PLANNED Bay-407( 4875) BAY DAILY Auto-recloser testing 02-08-2023 10:00:03 02-08-2023 16:00:03 PENDING
14 262 PLANNED 400/220 KV 315 MVA ICT 1(5735):400/220/66 kV GIS Gumma(HPPTCL) ICT DAILY Auto-recloser testing 02-08-2023 10:00:03 02-08-2023 16:00:03 PENDING
15 263 PLANNED ICT-2(5736):400/220/66 kV GIS Gumma(HPPTCL) ICT DAILY Auto-recloser testing 01-08-2023 10:00:03 01-08-2023 16:00:03 PENDING
16 275 PLANNED BUS-1(GUMMA GISABS400001):400/220 kV Gumma (GIS)(HPPTCL) BUS DAILY Auto-recloser testing 15-09-2023 10:00:29 15-09-2023 16:00:29 PENDING
17 276 PLANNED Gumma(400)(HPPTCL)-Panchkula(400)(HPPTCL) 1 LINE DAILY Auto-recloser testing 15-09-2023 10:00:29 15-09-2023 16:00:29 PENDING
18 277 PLANNED Bay-408( 4876) BAY DAILY Auto-recloser testing 15-09-2023 10:00:29 15-09-2023 16:00:29 PENDING
19 278 PLANNED Gumma(400)(HPPTCL)-Jhakri(400)(HPPTCL) 1 LINE DAILY Auto-recloser testing 15-09-2023 10:00:29 15-09-2023 16:00:29 PENDING
20 279 PLANNED Bay-406( 4874) BAY DAILY Auto-recloser testing 15-09-2023 10:00:29 15-09-2023 16:00:29 PENDING
21 280 PLANNED ICT-2(5736):400/220/66 kV GIS Gumma(HPPTCL) ICT DAILY Auto-recloser testing 15-09-2023 10:00:29 15-09-2023 16:00:29 PENDING
22 281 PLANNED 400 Kv Bus- 2 (Gumma)(1400001):400/220 kV Gumma (GIS)(HPPTCL) BUS DAILY Auto-recloser testing 16-09-2023 10:00:29 16-09-2023 16:00:29 PENDING
23 282 PLANNED Gumma(400)(HPPTCL)-Panchkula(400)(HPPTCL) 2 LINE DAILY Auto-recloser testing 16-09-2023 10:00:29 16-09-2023 16:00:29 PENDING
24 283 PLANNED Bay-405( 4873) BAY DAILY Auto-recloser testing 16-09-2023 10:00:38 16-09-2023 16:00:38 PENDING
25 284 PLANNED Gumma(400)(HPPTCL)-Jhakri(400)(HPPTCL) 2 LINE DAILY Auto-recloser testing 16-09-2023 10:00:38 16-09-2023 16:00:38 PENDING
26 285 PLANNED Bay-407( 4875) BAY DAILY Auto-recloser testing 16-09-2023 10:00:33 16-09-2023 16:00:33 PENDING
27 286 PLANNED 400/220 KV 315 MVA ICT 1(5735):400/220/66 kV GIS Gumma(HPPTCL) ICT DAILY Auto-recloser testing 16-09-2023 10:00:33 16-09-2023 16:00:33 PENDING
28 296 PLANNED 400/220/66 kV GIS Substation, Wangtoo(HPPTCL)-shorang(400KV)(PHTL) 2 LINE DAILY DCRM Testing 05-10-2023 09:00:13 05-10-2023 16:00:13 APPROVED
29 297 PLANNED Gumma(400)(HPPTCL)-Panchkula(400)(HPPTCL) 2 LINE DAILY periodical testing 17-10-2023 09:00:14 17-10-2023 18:00:14 PENDING
30 298 PLANNED Gumma(400)(HPPTCL)-Jhakri(400)(HPPTCL) 2 LINE DAILY periodical testing 17-10-2023 09:00:58 17-10-2023 18:00:58 PENDING
31 299 PLANNED ICT-2(5736):400/220/66 KV Gumma(HPPTCL) ICT DAILY periodical testing 18-10-2023 09:00:38 18-10-2023 18:00:38 PENDING
32 300 PLANNED Gumma(220)(HPPTCL)-220 KV Hatkoti(HPPTCL) 2 LINE DAILY periodical testing 18-10-2023 09:00:33 18-10-2023 18:00:33 PENDING
33 301 PLANNED 400/220 KV 315 MVA ICT 1(5735):400/220/66 KV Gumma(HPPTCL) ICT DAILY periodical testing 19-10-2023 09:00:33 19-10-2023 18:00:33 PENDING
34 302 PLANNED Gumma(220)(HPPTCL)-220 KV Hatkoti(HPPTCL) 1 LINE DAILY periodical testing 19-10-2023 09:00:33 19-10-2023 18:00:33 PENDING
35 303 PLANNED Spare Transformer(5739):400/220/66 KV Gumma(HPPTCL) ICT DAILY periodical testing 20-10-2023 09:00:33 20-10-2023 18:00:33 PENDING
36 304 PLANNED Gumma(400)(HPPTCL)-Panchkula(400)(HPPTCL) 1 LINE DAILY periodical testing 21-10-2023 09:00:38 21-10-2023 18:00:38 PENDING
37 305 PLANNED Gumma(400)(HPPTCL)-Jhakri(400)(HPPTCL) 1 LINE DAILY periodical testing 21-10-2023 09:00:38 21-10-2023 18:00:38 PENDING
38 329 PLANNED 400 KV Lahal(HPPTCL)-400 kV RAJERA(PG) 2 LINE CONTINUOUS Yearly Periodical testing 01-11-2023 09:00:59 30-11-2023 17:00:59 PENDING
39 330 PLANNED Bay No. 406-400kV TIE Bay( 5251) BAY CONTINUOUS Yearly Periodical Testing 01-11-2023 09:00:15 01-11-2023 17:00:15 PENDING
40 331 PLANNED 400 KV Lahal(HPPTCL)-400 kV RAJERA(PG) 2 LINE CONTINUOUS Yearly Periodical Testing 01-11-2023 09:00:44 01-11-2023 17:00:44 PENDING
41 332 PLANNED 400 KV LAHAL RAJERA CKT-2 (BAY-405)( 5129) BAY CONTINUOUS Yearly Periodical Testing 01-11-2023 09:28:07 01-11-2023 09:28:07 PENDING
42 333 PLANNED 220kV Bajoli Holi(HPPTCL)-220KV Lahal(HPPTCL) 1 LINE CONTINUOUS Yearly Periodical Testing 01-11-2023 09:31:52 01-11-2023 09:31:52 PENDING
43 334 PLANNED 220 KV LAHAL BAJOLI HOLI CKT-1 (BAY-E07)( 5137) BAY CONTINUOUS Yearly Periodical Testing 01-11-2023 09:36:16 01-11-2023 09:36:16 PENDING
44 335 PLANNED ICT-2 Bank( 5757):400 KV Lahal(HPPTCL) ICT CONTINUOUS Yearly Periodical Testing 02-11-2023 09:39:33 02-11-2023 09:39:33 PENDING
45 336 PLANNED Bay No. 402-ICT-2 Bank 400kV Side Bay( 5253) BAY CONTINUOUS Yearly Periodical Testing 02-11-2023 09:41:51 02-11-2023 09:41:51 PENDING
46 337 PLANNED Bay No. 202-ICT-2 Bank 220kV Side Bay( 5257) BAY CONTINUOUS Yearly Periodical Testing 02-11-2023 09:43:53 02-11-2023 09:43:53 PENDING
47 338 PLANNED Bay No. 403-400kV TIE Bay( 5250) BAY CONTINUOUS Yearly Periodical Testing 02-11-2023 09:46:11 02-11-2023 09:46:11 PENDING
48 339 PLANNED 220 KV LAHAL BUDHIL CKT-1 (BAY-E06)( 5139) BAY CONTINUOUS Yearly Periodical Testing 02-11-2023 09:49:55 02-11-2023 09:49:55 PENDING
49 340 PLANNED Bay No. 204-220kV Bus-Coupler Bay( 5255) BAY CONTINUOUS Yearly Periodical Testing 02-11-2023 09:52:18 02-11-2023 09:52:18 PENDING
50 341 PLANNED ICT-1 Bank( 5756):400 KV Lahal(HPPTCL) ICT CONTINUOUS Yearly Periodical Testing 04-11-2023 09:00:16 04-11-2023 17:00:16 PENDING
51 342 PLANNED Bay No. 404-ICT-1 Bank 400kV Side Bay( 5252) BAY CONTINUOUS Yearly Periodical Testing 04-11-2023 09:00:18 04-11-2023 17:00:18 PENDING
52 343 PLANNED Bay No. 203-ICT-1 Bank 220kV Side Bay( 5256) BAY CONTINUOUS Yearly Periodical Testing 04-11-2023 10:59:23 04-11-2023 10:59:23 PENDING
53 344 PLANNED Bay No. 403-400kV TIE Bay( 5250) BAY CONTINUOUS Yearly Periodical Testing 04-11-2023 09:00:30 04-11-2023 17:00:30 PENDING
54 345 PLANNED 105 MVA SPARE ICT( 5846):400/220/33 kV Lahal(HPPTCL) ICT CONTINUOUS Yearly Periodical Testing 04-11-2023 09:00:36 04-11-2023 17:00:36 PENDING
55 346 PLANNED Bay No. 401-Spare ICT 400kV Side Bay( 5254) BAY CONTINUOUS Yearly Periodical Testing 04-11-2023 09:00:11 04-11-2023 17:00:11 PENDING
56 347 PLANNED 400 KV Lahal(HPPTCL)-400 kV RAJERA(PG) 1 LINE CONTINUOUS Yearly Periodical Testing 03-11-2023 09:00:06 03-11-2023 17:00:06 PENDING
57 348 PLANNED 400 KV LAHAL RAJERA CKT-1 (BAY-407)( 5130) BAY CONTINUOUS Yearly Periodical Testing 03-11-2023 09:00:49 03-11-2023 17:00:49 PENDING
58 349 PLANNED Bay No. 406-400kV TIE Bay( 5251) BAY CONTINUOUS Yearly Periodical Testing 03-11-2023 09:00:52 03-11-2023 17:00:52 PENDING
59 350 PLANNED 220kV Holi-Lahal (D/C) line(HPPTCL)-Holi bajauli(Holi) 2 LINE CONTINUOUS Yearly Periodical Testing 03-11-2023 09:00:32 03-11-2023 17:00:32 PENDING
60 351 PLANNED 220 KV LAHAL BAJOLI HOLI CKT-2 (BAY-E08)( 5138) BAY CONTINUOUS Yearly Periodical Testing 03-11-2023 09:00:25 03-11-2023 17:00:25 PENDING
61 353 PLANNED 3-PH T/F( 5748):400 KV Lahal(HPPTCL) ICT CONTINUOUS Yearly Periodical Testing 03-11-2023 09:00:25 03-11-2023 17:00:25 PENDING
62 369 PLANNED 220 KV SUNDA HATKOTI CKT-2 (BAY-202)( 5155) BAY CONTINUOUS Annual Testing and maintenance 22-11-2023 09:00:00 22-11-2023 18:00:00 APPROVED
63 370 PLANNED 220/132 kV -T2(5752):220/132/66 KV Sunda(HPPTCL) ICT CONTINUOUS Annual testing and maintenance 22-11-2023 09:00:04 22-11-2023 18:00:04 APPROVED
64 371 PLANNED 220/132 kV -SINGLE PHASE SPARE(5754):220/132/66 KV Sunda(HPPTCL) ICT CONTINUOUS annual testing and maintenance 22-11-2023 09:00:04 22-11-2023 18:00:04 APPROVED
65 372 PLANNED 220 KV SUNDA HATKOTI CKT-1 (BAY-201)( 5154) BAY CONTINUOUS Annual testing and maintenance 23-11-2023 09:00:04 23-11-2023 18:00:04 APPROVED
66 373 PLANNED 220/132 kV -T1(5751):220/132/66 KV Sunda(HPPTCL) ICT CONTINUOUS Annual testing and maintenance 23-11-2023 09:00:04 23-11-2023 18:00:04 APPROVED
67 374 PLANNED 220 KV BUS -2(HPPTCLABS220013):220/132/66 KV Sunda(HPPTCL) BUS CONTINUOUS Annual testing and maintenance 22-11-2023 09:00:04 22-11-2023 18:00:04 APPROVED
68 375 PLANNED 132 KV BUS-1(HPPTCLABS132007):220/132/66 KV Sunda(HPPTCL) BUS CONTINUOUS Annual testing and maintenance 24-11-2023 09:00:04 24-11-2023 18:00:04 APPROVED
69 376 PLANNED 132 KV BUS-2(1132001):220/132/66 KV Sunda(HPPTCL) BUS CONTINUOUS Annual testing and maintenance 24-11-2023 09:00:04 24-11-2023 18:00:04 APPROVED
70 390 PLANNED 220/33 KV KARIAN(HPSEBL)-400 kV RAJERA(PG) LINE CONTINUOUS HPPTCL has planned to execute existing 220kV Bus extension work & erection of proposed 220kV, Bay No. D04 at 220/33kV GIS Substation Karian for connecting Karian Substation with HPPTCL 220/132kV GIS Majra Substation through Circuit-II. 01-01-2024 10:00:14 22-01-2024 17:00:14 REJECTED
71 391 PLANNED 220/33 KV -T1( 5832):220/33 KV KARIAN(HPSEBL) ICT CONTINUOUS to execute existing 220kV Bus extension work & erection of proposed 220kV, Bay No. D04 at 220/33kV GIS Substation Karian for connecting Karian Substation with HPPTCL 220/132kV GIS Majra Substation through Circuit-II. 01-01-2024 14:02:35 22-01-2024 14:02:35 REJECTED
72 392 PLANNED 220 kV CHAROR(HPPTCL)-220 kV BANALA(PG) 1 LINE DAILY Annual maintenance of 220 kV D/C Charor - Banala Transmission Line and Shifting of PLCC panels 04-01-2024 10:00:18 05-01-2024 17:00:18 PENDING
73 393 PLANNED 220 kV CHAROR(HPPTCL)-220 kV BANALA(PG) 2 LINE DAILY Annual maintenance of 220 kV D/C Charor - Banala Transmission Line and Shifting PLCC panels 04-01-2024 15:03:56 05-01-2024 15:03:56 PENDING
74 394 PLANNED 220/33 KV KARIAN(HPSEBL)-400 kV RAJERA(PG) LINE CONTINUOUS HPPTCL has planned to execute existing 220kV Bus extension work & erection of proposed 220kV , D04 Bay No. at 220/33kV GIS Substation Karian for connecting Karian Substation with HPPTCL 220/132kV GIS Majra Substation through Circuit-II. 01-01-2024 09:00:08 25-01-2024 17:00:08 PENDING
75 395 PLANNED 220/33 KV -T1( 5832):220/33 KV KARIAN(HPSEBL) ICT CONTINUOUS HPPTCL has planned to execute existing 220kV Bus extension work & erection of proposed 220kV , D04 Bay No. at 220/33kV GIS Substation Karian for connecting Karian Substation with HPPTCL 220/132kV GIS Majra Substation through Circuit-II. 01-01-2024 15:27:26 25-01-2024 15:27:26 REJECTED
76 396 PLANNED 220/33 KV -T1( 5832):220/33 KV KARIAN(HPSEBL) ICT CONTINUOUS HPPTCL has planned to execute existing 220kV Bus extension work & erection of proposed 220kV, Bay No. D04 at 220/33kV GIS Substation Karian for connecting Karian Substation with HPPTCL 220/132kV GIS Majra Substation through Circuit-II. 01-01-2024 09:00:08 25-01-2024 17:00:08 PENDING
77 420 PLANNED ICT-1 Bank( 5756):400 KV Lahal(HPPTCL) ICT CONTINUOUS For the repair/maintenance of OLTC DOVA chamber of 400/220/33kV, B-phase Autotransformer of ICT Bank-1. 06-02-2024 09:00:06 08-02-2024 19:00:06 PENDING
78 434 PLANNED 220 kV CHAROR(HPPTCL)-220 kV BANALA(PG) 1 LINE DAILY Annual maintenance of 220kV Charor - Banala Transmission line CKT-1 05-03-2024 09:00:17 06-03-2024 17:00:17 PENDING
79 435 PLANNED 220 kV CHAROR(HPPTCL)-220 kV BANALA(PG) 2 LINE DAILY Annual maintenance of 220kV Charor - Banala Transmission line CKT-2 05-03-2024 09:00:58 06-03-2024 17:00:58 PENDING